A blow molding machine can hold its cycle time, mold a clean bottle and still fail the safety walk-through on acceptance day. The guard you can reach around while the clamp closes, the E-stop that stops the main motor but leaves pressure on the mold, the two-hand control one hand can defeat: these are the faults that surface after the machine is on your floor, with the mold mounted and the order already late.
What Should You Test Before You Accept the Machine?
Test the safety functions, not the paperwork alone. At acceptance, open every guard and confirm the clamp stops and cannot close again until reset; test each E-stop; confirm the clamp cannot be moved with the pump off; check the cabinet against IEC 60204-1; and match the risk assessment to the machine you are buying.
Start at the clamp and the die. Open each guard while the clamp is closing and try to restart with the guard still open. The clamp should stop, refuse to close again and require a deliberate reset; a guard that only trips an alarm is not an interlock. Where an operator can reach into the die or blow-pin area, the machine needs two-hand control or hold-to-run, and releasing one button or the handle must stop the motion.
Then go to the hydraulics and the cabinet. With the mold closed and the pump stopped, the clamp must stay closed and must not drift; ask which valve holds it and where stored pressure is released before anyone reaches in. In the cabinet, check protective earth, door interlock on live parts, circuit labelling and component ratings against IEC 60204-1. That standard is a reference, not a badge on the machine.
Safety Functions and Their Pass Criteria
Use the table below as the acceptance sheet. Every line needs a witness, a result and a document.
| Safety function | What to test | Pass criteria | Document to request |
|---|---|---|---|
| Clamp guard interlock | Open the guard while the clamp closes; try to restart | Clamp stops, cannot close while the guard is open, restart needs a reset | Interlock cause-and-effect chart |
| Die and blow-pin guard | Reach test with a rod; open the guard during blowing | No hazardous motion with the guard open; blow air released or held as designed | Guard drawing with safety distances |
| Two-hand or hold-to-run control | Release one button or the handle in mid-stroke | Motion stops; both hands must re-engage to restart | Control page of the electrical schematic |
| Emergency stop | Press each E-stop at the clamp, carriage and panel | All hazardous motion stops; reset alone does not restart | E-stop circuit page and stop category |
| Clamp hydraulic lock | Stop the pump with the mold closed | Clamp stays closed and does not drift | Hydraulic schematic and valve list |
| Electrical cabinet | Earth, door interlock, labelling, ratings against IEC 60204-1 | No exposed live parts; circuits identified; components rated for the supply | Electrical schematic and component list |
| Risk assessment | Compare the ISO 12100 assessment with the machine delivered | Covers this model, mold, options and the guards actually fitted | Risk assessment and residual-risk list |
Swipe the table to see all columns →
How to Run the Test on Acceptance Day
Run the test in the order the operator meets the machine. Power up with the guards closed, then open one guard at a time and log the result. Press every E-stop, including the ones at the far end of the machine, and confirm that reset alone does not restart the clamp. Stop the pump with the mold closed and watch the clamp for drift while the pressure gauge is observed. Fill the die area with a test rod at the lowest safety distance and repeat the reach test at every opening.
Record the model, mold and options on the sheet. A risk assessment written for a single-station machine does not cover a double-station machine with a different clamp and take-off. If CE marking applies, check that the declaration and technical file name the model and configuration you are buying; if it does not, ask how the same safety functions are demonstrated.
Two people should sign: the operator and the maintenance technician. The operator tests reach and reset, the technician tests lockout points and stored energy. A guard that can be bypassed with a screwdriver is a fail, and the fix belongs in writing before the balance payment.
For the machine side, compare thesingle-station 0–16L rangeand thedouble-station 0–16L range; for the daily routines that keep guards closed, readoperator trainingandshampoo bottle production.
What to Send for a Quotation
Safety scope changes with the mold, the take-off and the destination, so a container size alone is not enough.
- Container drawing or sample: volume, neck, weight and wall target.
- Material and layer structure, for example HDPE or a multi-layer barrier.
- The model or series you are comparing, and the cavities you need.
- Destination country and the safety documents your buyer or authority expects.
- Take-off method: manual, robot or conveyor.
- Site supply voltage, compressed air and floor space.
- Delivery date, installation support and the language for manuals and training.
Source: E-SHION product data. Specifications are subject to change without notice; customization is available.
This guide is written for production and procurement decisions. It uses published figures where available and avoids unverified performance claims.