The machine is built, the balance payment is due, and the container is booked. You have never seen it run. A pre-shipment inspection is the last inexpensive moment to catch a 380 V machine ordered for a 415 V plant, a missing set of spares, or a mold number that does not match the contract. Once the container sails, every correction costs a second freight, a second customs entry and an idle line.
FAT and pre-shipment inspection are not substitutes
A factory acceptance test proves performance: your mold, your resin, your bottle. A pre-shipment inspection proves conformity: the right model, voltage, mold number, guards, documents, spares and packing. One is a trial, the other is a handover. If you can attend only one, attend the FAT and ask for a documented shipping check.
Buyers ask for a test report and receive a folder of photographs. That is not concealment; the two events are run by different teams. The FAT runs with the mold on the machine, led by the technical team. The shipping check is a documentation exercise, run by quality and logistics against the packing list. If the order names only one of them, you get the one the supplier finds easiest.
What a pre-shipment inspection covers
The scope is deliberately boring. A useful inspection is a line-by-line reconciliation between the machine in front of the inspector and documents you have already signed. Anything that cannot be checked against a document becomes an opinion, and opinions do not survive a language barrier or an ocean crossing.
- Nameplate: model code, serial number, year of manufacture and rated values, matching the order and the manual.
- Power supply: voltage, frequency, phase and control voltage, checked at the plate, the terminal markings and the transformer taps, not only in the quotation.
- Mold interface: mold number, cavity count, platen and tie-rod dimensions, and the tool that is actually packed with the machine.
- Safety items: guard doors, interlocks, emergency stops and warning labels in the language agreed.
- Documents: operation manual, electrical and hydraulic diagrams, spare-parts list, warranty terms, packing list.
- Spares and tooling: the contract spare-parts table, item by item, with quantities and ship dates for shortages.
- Packing: surface protection, wrapping, bracing inside the container, packing list fixed to the crate.
- Running record: dry run and function test, kept as video or a signed sheet.
Where each check happens in the build
The build passes five internal gates. Not every gate produces a record you can read, and the record is what an inspector works from. Ask which gates leave a signed sheet before you ask for an inspection.
| Stage | What is verified | Record you can receive |
|---|---|---|
| Incoming material | Plate, screw and barrel grade, purchased components | Incoming records; witness usually not arranged |
| Mechanical assembly | Frame, platens, clamp unit, extruder alignment, guards | Assembly photos on request |
| Electrical and hydraulic | Wiring, terminal torque, hose routing, pressure and leak test | Signed fitter checklist |
| Dry run and function test | All motions, heaters, parison programmer, alarms, interlocks | Test video and signed test sheet |
| Export packing | Surface protection, wrapping, bracing, packing list, loading | Loading photos and packing list |
Swipe the table to see all columns →
Most buyers never see these records. Ask for them to be kept in one file, with signed sheets, photographs and the packing list, and specify that the file arrives before the balance payment. A file assembled in advance is a quality system; one assembled after a complaint is an apology.
Put the inspection in the contract, not in the chat
Third-party inspection can be agreed before the order is placed. What makes it enforceable is specificity. Third-party inspection acceptable, written in a quotation, is not an agreement; it is a mood. Each line below belongs in the order or in an annex signed with it.
- Body: the inspection company named, or the class of body, with the final choice confirmed in writing before the deposit.
- Standard: the checklist and acceptance criteria, referenced by revision, never described as a visual check.
- Timing: the inspection window relative to the finish date, and how many days of notice you will receive.
- Place: before packing at the factory, or after packing and before loading.
- Witness points: which tests must be attended and which may be recorded on video.
- Report scope: photographs, video, signed checklist, non-conformity list with closure dates.
- Cost and re-inspection: who pays for the first visit, who pays after a non-conformity, and what happens on a failure.
- Release condition: the balance is released against the report, not against a photograph of the machine.
What a clean handover file looks like
One sequence removes most of the argument. Three weeks before the planned finish date, the sales engineer sends the draft packing list and nameplate data: model, voltage, frequency, mold number, serial number. One week before, the inspection window and the checklist revision are fixed in writing. On the day, the inspector marks every line pass, fail or not applicable, and photographs the nameplate, the mold stamp, the terminal markings and the loaded container. The report and the non-conformity list reach both sides in the same week, and the balance is released once the open items are closed or dated.
The earlier qualification steps are set out inthe factory tour checklist, and the first week after arrival followsthe startup and shutdown sequence. Clamp and platen data for the sizes most often shipped in this class are listed undersingle-station 0.1 to 16 L machinesanddouble-station 0.1 to 16 L machines.
What to send for a quotation
- Container: volume in litres and shape, whether bottle, jerrycan, wide-mouth jar or industrial part.
- Material and layer structure: HDPE, PP, PETG or multi-layer barrier, with the layer ratio if fixed.
- Output target: good parts per hour and the shift pattern, so cavity count can be checked against the extruder.
- Mold status: an existing mold with drawings and mold number, or a new mold to be quoted with the machine.
- Destination: country, port, voltage, frequency and phase.
- Inspection: whether you will attend the FAT, whether a third party inspects before shipment, and the checklist you want used.
- Documents and language: manual language, and any declaration or labelling your market requires.
- Site conditions: ceiling height, door width, floor loading and available power.
An inspection does not make a machine better. It makes the handover honest, and it gives both sides the same document to point at when something is missing.
Source: E-SHION product data. Specifications are subject to change without notice; customization is available.
This guide is written for production and procurement decisions. It uses published figures where available and avoids unverified performance claims.