A buyer with a 1 million bottle annual target often asks for two or three machines before anyone has measured a cycle. The annual number is the weakest input in the calculation. It says nothing about the peak month, the number of SKUs, the mold count or the real OEE. Start with the formula, then test the answer against the peak week and the extruder.
The short answer: one machine often covers 1 million bottles
Machine count = annual good parts ÷ (cavities × cycles per hour × operating hours × OEE). At 4,000 hours, a 2-cavity mold, a measured 12-second cycle and 85% OEE, one machine makes about 2.04 million 1 L bottles a year — twice the target. The same arithmetic for a 5 L bottle at 20 seconds still leaves one machine sufficient. The annual total rarely justifies a second machine on its own.
Build the calculation from measured inputs
Use the same five inputs for every container. Write down the source next to each one; a number without a source is a guess, not a plan.
- Annual good parts: the saleable quantity, after the reject rate, not the gross target.
- Cavities: the mold layout you are actually quoting, not the maximum the machine can take.
- Cycles per hour: 3,600 ÷ measured cycle time in seconds. Use a trial on the actual mold, material and wall.
- Operating hours: scheduled production hours after planned maintenance, holidays and changeovers.
- OEE: availability × performance × quality. Use your own trial or a documented line figure; 85% is an example, not a guarantee.
| Input | 1 L HDPE bottle | 5 L HDPE bottle | Where the number comes from |
|---|---|---|---|
| Annual good parts | 1,000,000 | 1,000,000 | Sales plan after reject allowance |
| Cavities | 2 | 2 | Mold layout being quoted |
| Measured cycle | 12 s | 20 s | Trial on the actual mold and material |
| Cycles per hour | 300 | 180 | 3,600 ÷ cycle time |
| Gross bottles per hour | 600 | 360 | Cavities × cycles per hour |
| OEE | 85% | 85% | Buyer's documented line figure |
| Good bottles per hour | 510 | 306 | Gross × OEE |
| Operating hours | 4,000 | 4,000 | Scheduled hours after maintenance |
| Annual good bottles, one machine | 2,040,000 | 1,224,000 | Good per hour × hours |
Swipe the table to see all columns →
The peak month, not the annual total, decides the second machine
Take the busiest month from your sales plan and run the same formula for that month's good parts and available hours. If the peak needs 1.4 machines, you either add capacity, extend hours, add cavities or hold stock. The annual average hides this. A second machine also needs a second mold or a changeover plan; a single mold shared across two machines does not double output.
Run a sensitivity check before you commit. A 10% slower cycle, a 5% lower OEE or two extra changeover hours per week can turn a comfortable one-machine plan into a two-machine month. Change one input at a time and write down the result; the goal is not a single answer but a range you can defend. If the peak month still fits one machine with a 15% margin, the annual plan is robust. If it does not, price the second machine and the second mold together, then compare that cost with overtime, inventory and a longer lead time. The same check applies to part weight: a heavier preform or a thicker wall raises kilograms per hour even when bottle count stays the same.
Product mix is the other multiplier. Four SKUs with colour and neck changes lose hours to purge, changeover and start-up. Add those hours to the denominator before you conclude that one machine is enough. If the mix is stable and the mold is dedicated, the annual arithmetic is closer to reality.
The cavity and cycle arithmetic is set out inblow molding cavity output calculation. If you already have a mold, readrunning an existing mold on a new machinebefore comparing models.
What to send for a quotation
A capacity quotation is only as good as the inputs behind it. Send these with the enquiry:
- Annual volume and the peak month, both in good parts.
- Container drawing, weight and wall target, so the melt demand can be checked.
- Cavity plan and whether the mold is new or existing.
- Measured cycle, or the trial plan that will produce one.
- Scheduled operating hours, shift pattern and planned maintenance.
- OEE or the current line's availability, performance and quality figures.
- Product mix, colour changes and changeover time per SKU.
- Destination, voltage and whether the line will run one product or several.
Compare the0.1–16 L single-station rangeanddouble-station range, then send the volumes through thecontact page.
Source: E-SHION product data. Specifications are subject to change without notice; customization is available.
This guide is written for production and procurement decisions. It uses published figures where available and avoids unverified performance claims.